2025 Street Maintenance Project

Background

In 2005, a Joint Powers Agreement (JPA) for Traffic Markings, Street Sweeping, Crack Sealing, Screening, and Seal Coating was executed by the cities of Coon Rapids, Andover, Brooklyn Center, Columbia Heights, and Fridley. Since 2005, six additional cities have joined the joint powers agreement (Ham Lake, East Bethel, Anoka, Mahtomedi, Circle Pines, and Mounds View). On December 11, 2017, the City Council authorized an amendment to the JPA to include the City of Arden Hills.

Project Overview

Each year, the City performs street and trail preservation activities in different parts of the city as part of a long-term program. Pavement preservation work for the 2025 construction season will include sealcoating, pavement markings, crack sealing and fog sealing within segments of the City's streets and trails as shown on the following:

A letter was sent to residents in June detailing the work planned and how it will impact their neighborhood. 2025 Street Maintenance Program Letter to Residents

Further information on Reclamite Pavement Maintenance in Arden Hills here.

Project Timeline

April 14: City Council accepted the resolution recommending the City of Coon Rapids award a contract for the 2025 Street Maintenance Program.

Week of June 23: Crack Seal installed

After July 6: Chip Seal street work to be performed

After July 31: Fog Seal to be performed

Mid-August: Reclamite Streets to be performed

End of August/Early September: Striping work to be done

Program Bid Tabulation

Access a copy of the 2025 Street Maintenance Program Bid Tabulation (PDF)